I want to hang a structure above my stand...
To organize a hanging structure above your stand, you need to:
  1. Familiarize yourself with the technical requirements of the pavilions at the exhibition site (Note! It is technically impossible to organize a hanging structure under the balconies of the first pavilion, under the protective net of the first pavilion balcony, and in the outdoor exhibition area!).
  2. Submit to the exhibition's technical service for approval of the hanging structure no later than 30 days before the start of installation work, including a technical assignment for the hanging structure and the project of the hanging structure, which should include the following information:
  • Drawing of the hanging structure indicating the weight of the unloaded and loaded structure, the calculated number of suspension points, and the calculated suspension height above the floor.
  • List and total weight of equipment to be hung on the structure.
  • Top view of the hanging structure on the grid indicating the location of the hanging structure relative to the pavilion.
  • Floor plan indicating the location of the stand in the pavilion.
  • Information about the representatives of the client company responsible for design, installation, and safety during the installation of the hanging structure.
  • For complex hanging structures, the Technical Service requires a static calculation of the hanging structure.
I want to hang a structure above my stand using my lifting mechanisms (winches) / trusses...
To organize a hanging structure above your stand using your lifting mechanisms (winches) / trusses, you need to:
  1. Familiarize yourself with the technical requirements of the pavilions at the exhibition site (Note! It is technically impossible to organize a hanging structure under the balconies of the first pavilion, under the protective net of the first pavilion balcony, and in the outdoor exhibition area!).
  2. Submit to the exhibition's technical service for approval of the hanging structure no later than 20 days before the start of installation work, including a technical assignment for the hanging structure, the project of the hanging structure, and the project for performing high-altitude work, which should include the following information:
  • Drawing of the hanging structure indicating the weight of the unloaded and loaded structure, the calculated number of suspension points, and the calculated suspension height above the floor.
  • List and total weight of equipment to be hung on the structure.
  • Top view of the hanging structure on the grid indicating the location of the hanging structure relative to the pavilion.
  • Floor plan indicating the location of the stand in the pavilion.
  • Information about the representatives of the client company responsible for design, installation, and safety during the installation of the hanging structure.
3. Provide an act of technical inspection (testing) of the trusses/lifting mechanisms, meeting the requirements.
These requirements are developed in accordance with:
  • The safety rules for hazardous production facilities using lifting equipment. Rostekhnadzor Order No. 533 of November 12, 2013 (as amended on April 12, 2016).
  • Occupational safety rules in theaters and concert halls. Order of the Ministry of Culture of the Russian Federation dated January 6, 1998.
  • GOST 8617-81. Extruded profiles made of aluminum and aluminum alloys. Technical conditions.
  • Technical documentation of the official distributor of Prolyte in Russia. Blackbook Technical materials Russian version 2015.
The act must contain the following sections, documents, and information:
  • Title page with the details of the organization that conducted the technical inspection, with the signatures of the heads, certified by the seals of the contractor and the client organizations.
  • Name of the lifting equipment.
  • Justification for conducting the tests.
  • List of determined indicators.
  • List of regulatory documentation.
  • Information about the instruments and tools.
  • List of tested equipment with identification numbers (inventory numbers), types, and quantities.
  • Description of the testing methodology.
  • Conclusions based on the test results.
  • Signatures certified by the seal of the organization that conducted the tests, experts with names, initials, and qualification certificate numbers for the right to conduct measurements.
  • Test acts of the lifting equipment, certified by the seal of the organization that conducted the tests, experts with names, initials, and qualification certificate numbers for the right to conduct measurements.
  • Copy of the license, certified in the prescribed manner, for the right to carry out industrial safety expertise.
  • Copies of the qualification certificates of the experts who conducted the tests, certified in the prescribed manner.
  • Copy of the certificate of accreditation of the laboratory that conducted the measurements, certified in the prescribed manner.
The validity period of the acts of technical inspection of lifting equipment is 1 year.
  • For complex hanging structures, LLC "Technical Operator" may request a static calculation of the hanging structure.